|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
![]() |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Hearings: Testimony |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
Project 90 Land Development. As the table illustrates, capacity in the currently developed area of Arlington National Cemetery is becoming more concentrated and will be exhausted by 2013. In order to extend the Cemetery’s useful life to 2025, it is necessary to develop the 40 acres of open land within its current boundaries known as Project 90. This involves the development of gravesite areas, roads, utilities and a boundary wall with niches for the placement of cremated remains. Approximately 26,000 additional gravesites and 5,000 niches will be provided when the development is complete. The Project 90 land development effort is fully designed and $9.4 million in construction funds for Phase I were appropriated in FY 2002 and FY 2003. Phase I consists of grading the site, relocating utilities, constructing roads and landscaping gravesite areas. Construction of Phase I began in FY 2004 and is scheduled to be finished in FY 2007. The FY 2005 budget included $5 million for Phase II of Project 90. In a letter dated February 1, 2006, we informed this subcommittee that $3,100,000 were being reprogrammed in FY 2006 to address a cost increase resulting from inflation and the need to pay for a 48-inch storm drain line as part of the first phase of the project. Phase II primarily entails construction of a new boundary niche wall that will hold the ashes of cremated remains on the inside of the wall. The niches and covers will be the same size and resemble those currently used at the existing Columbarium Complex. After allowing sufficient time for ground settlement, it is anticipated that construction of Phase II would begin in FY 2007 and be completed in FY 2009. At the current rate of niche use it is estimated that the additional niches will be needed by the year 2012. Utility Relocations. Arlington County is planning to replace an aging sanitary sewer line that runs through Arlington National Cemetery with a new line known as the Potomac Interceptor. The presence of the existing sewer line prevents burials in approximately ten acres of land along Eisenhower Drive. The new sewer line would be placed directly under the existing roadway, and if the other utilities (i.e., electric, telephone and water) that run through that area are also relocated, it is estimated that approximately eight to ten thousand more gravesites could be developed. BUDGET DETAILSThe budget is made up of three programs -- Operation and Maintenance, Administration, and Construction. The principal items contained in each program are described below. Operation and Maintenance ProgramThe budget for the Operation and Maintenance program is $17,588,000. It provides for the cost of operations necessary to conduct an average of 25 funeral services per day, accommodate approximately four million visitors each year, and maintain 652 acres of land and associated infrastructure. This program supports 93 of the cemeteries’ total of 99 full time equivalent (FTE) work-years. Contractual services comprise $9,200,000, or 52 percent, of the Operation and Maintenance program. Aministration ProgramThe budget includes $1,431,000 for the Administration program, which provides for essential management and administrative functions, including staff supervision of Arlington and Soldiers’ and Airmen’s Home National Cemeteries. Budgeted funds will provide for personnel compensation, benefits, and reimbursable administrative support services provided by other government agencies. This program supports the balance of the cemeteries’ workforce of six FTE work-years. Construction ProgramThe Construction program’s budget is $7,531,000. The following two major projects are particularly important to increase the capacity of Arlington National Cemetery, so that additional space can be made available for burials and inurnments. The Millennium Project. This project consists of three parcels of land. The first parcel (7 acres) is land within the boundaries of Arlington National Cemetery made available by demolition of the old warehouse buildings. The second parcel (12 acres) was transferred to the Cemetery from the National Park Service on January 28, 2002, pursuant to the authority contained in Section 2863 of Public Law 107-107, the National Defense Authorization Act for FY 2002. The final piece of the Millennium Project is a 13-acre parcel of adjacent land formerly owned by Fort Myer (picnic area), which was transferred to the Cemetery on January 21, 2004, in accordance with Section 2882 of the FY 2000 Defense Authorization Act (Public Law 106-65). Design of the Millennium Project began last year with funds appropriated in FY 2004. The first phase of construction is anticipated to start in FY 2007 and $5,904,000 is included to primarily address storm water runoff that brings large amounts of water into the Cemetery from heavily developed portions of Fort Myer. This is a preliminary estimate that is subject to refinement as more design work is completed. Phase IVB Columbarium Complex. As the option for cremation becomes more acceptable and because eligibility in the Columbarium at Arlington National Cemetery is less restrictive than eligibility for in-ground interment, use of the Columbarium has been and will continue to increase. The recently completed Phase IV A court has 7,672 niches and Phase IV B will have about the same number. Construction of Phase IV B will begin in Fiscal Year 2006 to ensure that niches will be available when required. The following table displays niche capacity and how long that capacity is expected to last, based on current usage. Note that the niche capacity shown in the table for the undeveloped area includes Phase IV B of the Columbarium and the Project 90 Phase II boundary niche wall, both of which are funded, but does not include the Millennium Project. Niche capacity provided in the Millennium Project will not likely be available until FY 2017. The table does not reflect future land expansion projects programmed in the Ten-year Capital Investment Plan, such as the Navy Annex and Ft. Myer parking lot, which are currently authorized and addressed in the Concept Land Utilization Plan.
TOMB OF THE UNKNOWNSA crack has developed in the marble stone that marks the Tomb of the Unknowns. Repair or replacement options are being considered as part of the National Historic Preservation Act consultation process. At the conclusion of that process, we will know when the work will need to be done and how much it will cost. We will include any funding needs associated with the repair or replacement in future budgets. Mr. Chairman, this concludes my testimony. We will be pleased to respond to questions from the Subcommittee.
|
Return to Witness List
| |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||